The planning content of the major construction period nodes of the project

author:Deng Youdong excellent management
The planning content of the major construction period nodes of the project

The planning content of the major construction period nodes of the project

Major nodes include control unit project nodes, milestone division project nodes, annual project nodes, etc. According to the relevant provisions of the bidding documents, contract documents, major change negotiations, etc., determine the milestone nodes, the project nodes of the controlling unit and the total construction period. According to the general schedule, annual schedule, monthly schedule, and special schedule of important projects, determine the project nodes of the control unit and the annual project nodes.

According to the requirements of the contract duration, establish the node control procedures for the construction period, prepare the schedule plan, strengthen the construction progress control, set up the progress early warning, and form the node management record; Ensure that the construction period required by the owner is more than 2-3 months in advance.

1. Node management and control procedures

Node management and control procedures are formulated according to the characteristics of the project.

The planning content of the major construction period nodes of the project

Figure 1 Node controller

2. Preparation of node plan

The planning content of the major construction period nodes of the project

Node scheduling

1. Preparation of control schedules

According to the requirements of the construction contract and bidding plan, construction organization design, project implementation plan and other documents, the project department refines the control schedule, prepares the general construction schedule, the main node control plan, and the monthly schedule, and reports it to the enterprise, the construction party, and the supervision unit for approval.

2. Prepare operational schedules

The project department shall, according to the requirements of the control schedule, prepare the weekly schedule and the schedule of important nodes, and implement the plan to each professional or work area.

3. Review the work team schedule

The project department shall require each operation team to submit the general schedule, node control plan and monthly schedule plan in line with the general schedule and control plan of the project, and submit it to the project department for approval and implementation.

3. Node progress control

At the end of each month (week), the project department shall, according to the requirements of the control schedule and the requirements of the owner and the supervisor for the schedule, as well as the completion of the production and schedule of the previous month (week), organize the project production management personnel to hold a special meeting to inform the completion of the production and progress of the previous month (week), discuss and decide the production and schedule requirements of the next month (week), coordinate the on-site construction environment, labor, machinery and other resource conditions, solve the problems raised by the operation team that need to be coordinated and solved, and form a formal operational schedule for the next month (week).

The planning content of the major construction period nodes of the project

Node progress control

The project department shall carry out information management and image management of the on-site project progress, fill in and update the construction progress information in a timely manner in the integrated project management system, and post and maintain the schedule in an appropriate conspicuous position in the on-site office.

The on-site engineer should strictly supervise the implementation of the schedule by each operation team, and effectively use rewards and punishments to promote the management of subcontracting schedule.

Fourth, node progress warning

The project management department shall monitor the progress of the project site according to the schedule, and if the construction progress is delayed, the project progress shall be classified according to the following standards, and an early warning signal for progress management shall be issued.

Table 1 Project node progress warning

The planning content of the major construction period nodes of the project
The planning content of the major construction period nodes of the project

About the author: WeChat public account "Deng Youdong Studio"