June 30th
Constructed by China Construction Eighth Bureau
National Regional Medical Center Construction Project
Key construction projects in Hebei Province
Hebei Hospital Project of Xuanwu Hospital of Capital Medical University
Fully completed
184 days ahead of the contract period!
Hebei · Shijiazhuang
The total construction area of the project is about 93,000 square meters
The construction content includes outpatient building, emergency building, etc
It is a national regional medical center during the "14th Five-Year Plan" period
The second batch of pilot projects
It is also promoted by Beijing and Hebei
Specific measures of the Beijing-Tianjin-Hebei coordinated development strategy
Hebei Province will be further improved
Regional radiation capacity of high-quality medical resources
In order to realize that the masses "do not leave the province when they are seriously ill".
The project was awarded the high-quality structural engineering of Hebei Province
Hebei Province construction safety and civilization standardization
"Cloud Observation" project and other honors
And successfully passed the acceptance of the Hebei Provincial Construction Industry Science and Technology Plan Project.
Efficient construction: ingenuity and ingenuity help perfect performance
The two foundation pits of the project are 18 meters deep
It is adjacent to the natural foundation of the original building
The initial scheme is partition excavation and partition construction
The project team has made rigorous, scientific calculations
Design excavation schemes under different geological conditions
Platen tests are carried out on natural foundations
The actual bearing capacity of the foundation is obtained
and held an on-site meeting with all parties involved
Adjust the initial scheme to a large overall excavation
Adopt the "original building on both sides."
Synchronous excavation construction method of deep foundation pit"
On the basis of ensuring the safety of the original building
Finish the cut before the rainy season
Save more than 60 days of construction time.
The outer frame is generally used for the construction of the main structure and the secondary structure
The project team also used the outer frame for the construction of the curtain wall keel
During the construction of the main structure
The outer frame reserves space for curtain wall construction
During the construction of the secondary structure
Intervene in the curtain wall construction in advance
Carry out the construction of the main and secondary keels of the curtain wall
When the outer frame is dismantled, the keel construction is completed
After that, the curtain wall glass is installed with a hanging basket for closure
Save more than 30 days of construction time.
Digital Construction: Strive for perfection to ensure first-time excellence
The mechanical and electrical engineering of the project is large, multi-special, and complex
Construction management is difficult
The project team is comprehensively arranged through BIM
Summarize and coordinate the pipelines of various disciplines into a unified model
Its modeling accuracy reaches the LOD500 (highest) level
A total of 541 pipeline crossings and collisions have been eliminated
Effectively avoid on-site demolition and rework
During the construction process, check the molding effect at any time
Ensure that the project construction is excellent at one time.
▲ Schematic diagram of complex rebar intersection nodes
At the same time, the project team leveraged Revit software
Perform detailed modeling of steel members
Optimize the arrangement of the intersection nodes of steel columns and complex steel bars
Between section steel, rebar, embedded parts, and concrete
Actual stakeout simulations are carried out in relative arrangement
Through construction progress simulation, process simulation, animation walkthrough, etc
Visually compare construction plans
Adjust and optimize the construction plan in time
Boost productivity.
Smart O&M: 5G Technology Empowers the "Strongest Brain"
The project focuses on building a "smart medical hospital"
Deeply integrate 5G technology into the medical system
Among them, the 5G command center can be realized
From pre-hospital first aid, in-hospital treatment to discharge follow-up
The whole process of medical behavior is safe and controllable
Intelligent early warning and "medicine and health care" integration
"Let the information run more and let the masses run less errands"
Improve the utilization rate of medical resources and the efficiency of diagnosis and treatment.
(The figure shows non-real data)
The intelligent system installed in the 5G command center
It is the "strongest brain" of the hospital
It integrates medical treatment, management and service
It is equipped with a medical consumables operation monitoring system
Unified Resource Monitoring System (Operations Management)
5G emergency channel, VR visit system and other functional modules
At the same time, the system builds a remote consultation platform
Let patients enjoy it without having to save money
Medical resources and technology of Beijing Xuanwu Hospital.