laitimes

184 days in advance! The construction project of another national regional medical center was fully completed

author:MOB推荐

June 30th

Constructed by China Construction Eighth Bureau

National Regional Medical Center Construction Project

Key construction projects in Hebei Province

Hebei Hospital Project of Xuanwu Hospital of Capital Medical University

Fully completed

184 days ahead of the contract period!

184 days in advance! The construction project of another national regional medical center was fully completed

Hebei · Shijiazhuang

The total construction area of the project is about 93,000 square meters

The construction content includes outpatient building, emergency building, etc

It is a national regional medical center during the "14th Five-Year Plan" period

The second batch of pilot projects

It is also promoted by Beijing and Hebei

Specific measures of the Beijing-Tianjin-Hebei coordinated development strategy

Hebei Province will be further improved

Regional radiation capacity of high-quality medical resources

In order to realize that the masses "do not leave the province when they are seriously ill".

The project was awarded the high-quality structural engineering of Hebei Province

Hebei Province construction safety and civilization standardization

"Cloud Observation" project and other honors

And successfully passed the acceptance of the Hebei Provincial Construction Industry Science and Technology Plan Project.

Efficient construction: ingenuity and ingenuity help perfect performance

184 days in advance! The construction project of another national regional medical center was fully completed

The two foundation pits of the project are 18 meters deep

It is adjacent to the natural foundation of the original building

The initial scheme is partition excavation and partition construction

The project team has made rigorous, scientific calculations

Design excavation schemes under different geological conditions

Platen tests are carried out on natural foundations

The actual bearing capacity of the foundation is obtained

and held an on-site meeting with all parties involved

Adjust the initial scheme to a large overall excavation

Adopt the "original building on both sides."

Synchronous excavation construction method of deep foundation pit"

On the basis of ensuring the safety of the original building

Finish the cut before the rainy season

Save more than 60 days of construction time.

184 days in advance! The construction project of another national regional medical center was fully completed

The outer frame is generally used for the construction of the main structure and the secondary structure

The project team also used the outer frame for the construction of the curtain wall keel

During the construction of the main structure

The outer frame reserves space for curtain wall construction

During the construction of the secondary structure

Intervene in the curtain wall construction in advance

Carry out the construction of the main and secondary keels of the curtain wall

When the outer frame is dismantled, the keel construction is completed

After that, the curtain wall glass is installed with a hanging basket for closure

Save more than 30 days of construction time.

Digital Construction: Strive for perfection to ensure first-time excellence

184 days in advance! The construction project of another national regional medical center was fully completed

The mechanical and electrical engineering of the project is large, multi-special, and complex

Construction management is difficult

The project team is comprehensively arranged through BIM

Summarize and coordinate the pipelines of various disciplines into a unified model

Its modeling accuracy reaches the LOD500 (highest) level

A total of 541 pipeline crossings and collisions have been eliminated

Effectively avoid on-site demolition and rework

During the construction process, check the molding effect at any time

Ensure that the project construction is excellent at one time.

184 days in advance! The construction project of another national regional medical center was fully completed

▲ Schematic diagram of complex rebar intersection nodes

At the same time, the project team leveraged Revit software

Perform detailed modeling of steel members

Optimize the arrangement of the intersection nodes of steel columns and complex steel bars

Between section steel, rebar, embedded parts, and concrete

Actual stakeout simulations are carried out in relative arrangement

Through construction progress simulation, process simulation, animation walkthrough, etc

Visually compare construction plans

Adjust and optimize the construction plan in time

Boost productivity.

Smart O&M: 5G Technology Empowers the "Strongest Brain"

184 days in advance! The construction project of another national regional medical center was fully completed

The project focuses on building a "smart medical hospital"

Deeply integrate 5G technology into the medical system

Among them, the 5G command center can be realized

From pre-hospital first aid, in-hospital treatment to discharge follow-up

The whole process of medical behavior is safe and controllable

Intelligent early warning and "medicine and health care" integration

"Let the information run more and let the masses run less errands"

Improve the utilization rate of medical resources and the efficiency of diagnosis and treatment.

184 days in advance! The construction project of another national regional medical center was fully completed

(The figure shows non-real data)

The intelligent system installed in the 5G command center

It is the "strongest brain" of the hospital

It integrates medical treatment, management and service

It is equipped with a medical consumables operation monitoring system

Unified Resource Monitoring System (Operations Management)

5G emergency channel, VR visit system and other functional modules

At the same time, the system builds a remote consultation platform

Let patients enjoy it without having to save money

Medical resources and technology of Beijing Xuanwu Hospital.

Read on