laitimes

Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow

author:Guangzhou Yuexiu released
Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow
Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow

To provide it to citizens and friends

A safer, more reliable gas supply

Yuexiu District will build the Erma Road (East 1st Street to East 8th Street) area

Renovation of old gas pipeline network

Construction will begin on July 3

The project adopts the mode of "sectional construction".

Please contact the public who are passing through this section of the road

Surrounding residents should pay attention to travel safety

📢📢📢

Construction section:

Yuexiu District Jianjian Erma Road (East 1st Street to East 8th Street) area, with a total length of about 900 meters

Construction Date:

July 3, 2024 to September 19, 2024

Construction time:

08:00-22:00 daily

Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow

Schematic diagram of construction

Q&A on matters related to this construction project

↓ ↓ ↓

Q: Why is this old gas pipeline network renovation project being carried out?

01

A: The main purpose of upgrading is to ensure the safety of public gas use.

According to the relevant person in charge of the gas company, the buried gas pipeline in the area was completed in 1992, and the pipeline material is seamless steel pipe, and the life of seamless steel pipe is generally 25 years, and it is easy to be corroded by stray current, resulting in perforation and gas leakage, causing potential safety hazards.

In this construction, the pipeline will be replaced with PE pipe, which will not be corroded by stray currents and will have a longer service life. The person in charge said, "The gas pipeline in the construction section has been used for more than 30 years, affected by factors such as the aging of the anti-corrosion layer of the pipeline and stray current, the corrosion of the medium-pressure gas pipeline is serious, and the original gas pipeline needs to be replaced in time to eliminate the potential safety hazards caused by pipeline corrosion and gas leakage." According to the actual situation of the construction site, some buried pipes will also be replaced with galvanized steel pipes on the roof. ”

In this gas pipeline renovation project in the area, the West Branch of Guangzhou Gas Group Co., Ltd. will strictly comply with the requirements of the "Notice of the General Office of the State Council on Printing and Distributing the Implementation Plan for the Aging Renewal and Transformation of Urban Gas Pipelines (2022-2025)" and the "Notice of the Guangzhou Municipal Urban Management and Comprehensive Law Enforcement Bureau on Further Improving the Aging Assessment and Renovation of Gas Pipeline Facilities" and other documents, and carry out technical transformation of the aging pipeline network of the construction of the Erma Road (East 1st Street to East 8th Street) section in Yuexiu District. Eliminate the hidden danger of pipeline corrosion and leakage, and effectively maintain the safety of people's lives and property and the safe operation of the city.

Q: Will residents' travel be affected during construction?

02

A: Please rest assured that the gas company will do its best to ensure that both construction and travel are correct.

It can be seen from the above construction time that the construction time is basically concentrated during working hours, which can minimize the impact on the daily life and travel of citizens. According to the person in charge of the relevant work of the gas company, the project adopted the "sectional construction" mode, and completed the road breaking, excavation, downpipe, backfill and temporary repair of the road surface on the same day, and restored traffic. Ensure that construction and travel are correct.

In addition, before the start of construction, the construction unit posted construction notices in the construction area, and notified the property groups and building owners in the surrounding communities, so as to inform the citizens and friends of the construction information through multiple channels.

Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow
Watch out for detours! Construction of the Erma Road area in Yuexiu District will start tomorrow

At the same time, during the construction period, the construction unit will strictly control the working time of the machinery that produces loud noise, so as to minimize the impact of noise on the surrounding residents. Construction time is 08:00-22:00. The construction process that produces a lot of noise is completed as much as possible in a time period that does not interfere with the rest of nearby residents.

During construction, it is necessary to enclose part of the inner streets and alleys of Jianshe Erma Road (East 1st Street to East 8th Street) in Yuexiu District in sections. During the construction period, construction tips and traffic guidance personnel will be set up, so please pay attention to the guidance and follow the guidance for safe and orderly passage.

Because of the construction to the general public friends

inconvenience

Thank you for your understanding

If you have any comments or suggestions on the project

Please contact 13178808708 (Zhu Gong)

【Category: Original】

Source: Information Times, Guangzhou Gas Group Co., Ltd. West Branch Editor: Wu Lesi Proofreader: Jiang Jintong Editor: Liu Siming Editor: Zhan Pingping

Read on