The reservoir dredging project is not only related to the normal operation of the reservoir's own flood control, irrigation and water supply functions, but also directly related to the production and life of the people, and is an important measure to benefit the people's livelihood. Recently, the Jiefang Village Reservoir has seized the low-water level operation period of the reservoir, accelerated the dredging and remediation of the reservoir, and laid a solid foundation for water supply to increase agricultural production and income in the county.
At the dredging construction site of the Jiefang Village Reservoir, several large excavators roared and waved their "long arms" to excavate the silt. The earthmoving truck shuttles back and forth, and the excavated sludge is transported to the designated place in time for proper disposal.
"The dredging project of Jiefang Village Reservoir began on July 1, dredging 300,000 cubic meters, using the low water level of the reservoir to complete the dredging task, hundreds of vehicles are currently carrying out operations, and the dredging work is proceeding smoothly." Wang Xinglong, the person in charge of the dredging bid section of the Jiefang Village Reservoir Risk Removal and Reinforcement Project, said.
In order to ensure the high quality and efficient progress of the project, the construction management office of the Jiefang Village Reservoir Risk Removal and Reinforcement Project strictly controls the progress of the project, focuses on the dredging of the reservoir, pays close attention to each work link, selects technical backbones to be stationed at the construction site, tracks and manages the whole construction process, pays close attention to the quality of the project, and coordinates and solves the difficulties and problems encountered in the construction process in a timely manner.
"The risk removal and reinforcement included in the 300,000 cubic meters of reservoir dredging task, through this dredging can effectively improve the storage capacity of the Jiefang Village Reservoir, and has a great role in alleviating the drought in the irrigation area." Xie Xingwan, deputy director of the Jiefang Village Reservoir Management Institute in Jinta County, said.
After the completion of the dredging project of Jiefang Village Reservoir, the irrigation capacity of the reservoir will be effectively improved, and the conditions for agricultural irrigation in the Yuanyang Irrigation Area will be vigorously improved, so as to provide more solid water conservancy support for the county's economic and social development and people's livelihood and well-being.
(Author: Guo Yu, Cao Hongzu)