laitimes

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

A few days ago, the Guangzhou Municipal Transportation Bureau officially issued the "14th Five-Year Plan for Transportation in Guangzhou" (hereinafter referred to as the "Planning").

During the "14th Five-Year Plan" period, Guangzhou will be built into a domestic large-scale circulation center node city and a domestic and international dual-cycle strategic link city, and a national central city and a comprehensive gateway city construction to a new level.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

It is worth mentioning that during the 14th Five-Year Plan period, the investment in continued construction projects was 370.7 billion yuan, and the investment in newly started projects was 280 billion yuan, totaling 650.7 billion yuan. The rail category accounted for the largest proportion, reaching 29.03%, with an investment of 151.1 billion yuan in continued construction projects and 37.8 billion yuan in newly started projects, totaling 188.9 billion yuan.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Take a look at the planning of some transportation hubs:

aviation

Comprehensively enhance the international competitiveness of Baiyun Airport's international aviation hub, promote the complementary and coordinated development of regional airport clusters, and build a world-class airport cluster in the Greater Bay Area with Baiyun International Airport as the core.

● By 2025, it will build a first-class gateway hub airport with 5 runways and 3 terminals, and achieve the passenger throughput capacity of Baiyun International Airport exceeding 100 million passengers.

● Combined with urban emergency, tourism and other needs, plan and build general airports such as Nansha, Huangpu, and Conghua to improve general aviation service capabilities.

Promote the airport 30 minutes directly to the central city, 1 hour to the Pearl River Delta cities, and 3 hours to the Pan-Pearl River Delta cities.

● It is planned to introduce high-speed railways, intercity railways and urban railways to form an efficient and convenient multi-level air-rail intermodal transport system. In terminal T3, baiyun airport high-speed rail station is set up, and the main line introduces the Guangzhou-Zhuhai (Macao) high-speed railway and the Guanghe high-speed railway, and builds a "crossover" external high-speed railway channel of Baiyun Airport that radiates north and south and connects east and west.

● Terminals T1, T2 and T3 have separate stations to introduce Suishen Intercity (Xintang to Guangzhou North Railway Station via Baiyun Airport) and Guangzhou-Foshan Ring Line (Guangzhou South Railway Station to Baiyun International Airport) into Baiyun Airport in series.

The new plan introduces the intercity from Fangcun to Baiyun Airport to further improve the fast track channel between Baiyun Airport and the central urban area of Guangzhou.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

shipping

Comprehensively enhance the comprehensive service function of international shipping, and promote the development of Guangzhou Port from an international port to a world-strong port. Optimize the port layout, enhance the level of specialization, scale and intelligence of Guangzhou Port, become an important gateway to the Guangdong-Hong Kong-Macao Greater Bay Area, and serve the pan-Pearl River Delta region and the international shipping hub of the national "Belt and Road".

Study and accelerate the adjustment of the planning plan of Nansha Port Area and Huangpu Port Area, orderly promote the transformation and upgrading of the inner port area and the old port operation area of Huangpu Port Area, gradually rebuild a number of passenger, yacht and cruise terminals, study and plan water buses, and develop the water leisure tourism industry.

Construction of professional deep-water berths in the Nansha Port Area and the southern wharf area of Xinsha Port District. Accelerate the implementation of the fourth phase of the Nansha Port Area Project, the Nansha Port Area Near-Ocean Wharf Project, the Nansha Port Area Grain and General Wharf Expansion Project, and the Construction of the General Berth No. 11-12 in Xinsha Port Area. Accelerate the preliminary work of the Guangzhou LNG Emergency Peak Shaving Station supporting the LNG terminal project and the Huangpu International Cruise Terminal project.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Railway hub

Comprehensively strengthen Guangzhou's position in the national railway network, implement the railway hub energy level upgrading project, smooth international channels, and build a world-class railway hub connecting the whole country, radiating Southeast Asia, connecting Eurasia and the Guangdong-Hong Kong-Macao Greater Bay Area Railway Center.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

● Expand capacity in the north direction, promote the construction of the Guangzhou-Qingdao-Yong high-speed railway and the Guizhou-Guangzhou high-speed rail connection line, promote the Guizhou-Guangzhou high-speed rail quality improvement project, and expand the capacity of the northbound corridor in the Guangdong-Hong Kong-Macao Greater Bay Area;

● Connect east and west, accelerate the construction of the Guangzhou-Shantou high-speed railway, the Guangzhou-Cham high-speed railway, and the Shenzhen-Jiangjiang railway, study and promote the construction of the Guanghe high-speed railway, and support the province to build a new pattern of "one nuclear, one belt and one region";

● Southbound integration, promote the construction of the Guangzhou-Zhuhai (Macao) high-speed railway, plan a new guangzhou-Shenzhen high-speed rail channel, cooperate with the national research to promote the layout of the super-city high-speed maglev channel and the construction of experimental lines, strengthen the Guangzhou-Shenzhen twin-city linkage, and improve the level of interconnection with the east-west poles of the Greater Bay Area.

● Accelerate the construction of the Guangzhou-Guangzhou South Liaison Line, the Guangzhou East to Xintang 56th Line, and the Guangzhou-Guangzhou East 34th Line, introduce high-speed rail into the central area, improve the railway corridor capacity in the central area, and strengthen the interconnection of regional hubs.

Accelerate the construction of a passenger transport hub pattern of "multi-station layout, multi-point to-departure, passengers inside and outside the cargo, and interconnection".

● Build Baiyun Station and upgrade Guangzhou Railway Station and Guangzhou East Railway Station, build a "three-station in one" closely linked central urban area combination hub, and improve the overall service capacity of the railway hub in the central area.

● Build Yuzhu Station, Zengcheng Station and Baiyun Airport Station, expand Guangzhou North Railway Station as an important hub passenger station in the north, and strengthen the support for hub services in key areas.

● Study and enhance the status of Nansha railway hub and promote the construction of a regional comprehensive transportation center in Nansha.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Intercity rail network

Jointly build an intercity railway network that radiates "axle support and polar axis radiation" in the province. Realize 60-minute direct rail access between Guangzhou and cities in the Guangdong-Hong Kong-Macao Greater Bay Area, 30-minute interconnection between Guangzhou-Foshan and Suiguan centers, and 30-minute direct access between the central urban area and Nansha sub-center and peripheral groups.

-- Building an interconnected intercity railway network.

Accelerate the construction of 6 intercity railways, including the Guangzhou-Foshan Ring Line from Guangzhou South to the Airport Section, the Guangzhou-Foshan Ring Line from Foshan West Station to guangzhou South Station (Guangzhou Section), the Guangqing Intercity Phase II (Guangzhou North to Guangzhou Section), the Foguan Intercity (Guangzhou South to Wanghong Section), the Suiguan-Shenzhen Intercity (Xintang to Baiyun Airport Section), and the Suiguan-Shenzhen Intercity Pazhou Branch Line, and study and promote the Guangzhou-Foshan Ring Line from Foshan West to Guangzhou North Section (Guangzhou Section), the Zhongnan Tiger Intercity, the Zhaoshun South Intercity, and the Guangzhou-Foshan River Pearl Intercity, forming a "ring + radial" intercity railway skeleton network. Strengthen the radiation capacity of the hub area and improve the level of connectivity with the core cities of the Bay Area.

-- Strengthen the integration and connection with the surrounding urban rails.

Accelerate the construction of four lines from Guangzhou East to Huadu Tiangui Intercity, Fangcun to Baiyun Airport Intercity, Foshan to Dongguan Intercity via Guangzhou, nansha to Zhuhai (Zhongshan) Intercity, etc.; jointly carry out rail transit planning research in Guangzhou Metropolitan Area in conjunction with surrounding cities, and build an integrated rail transit network system serving different travel purposes such as business and inter-city commuting in the metropolitan area.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

subway

-- Accelerate the construction of multi-level urban rail transit networks.

Promote the construction of high-speed rails and strengthen the rapid connection between the main urban area and the sub-center and the peripheral urban areas. Accelerate the construction progress of five high-speed metro lines, including Metro Line 18 and Line 22, as well as five fast subway lines, including The Eastern Extension of Line 3, the Second Phase of Line 7, the Western Extension of Line 7, the Second Phase of Line 13, and the Second Phase of Line 14.

Encrypt the general speed rail line network in the main urban area, improve the coverage of rail transit services, complete the construction of four urban rail transit lines such as the eastern extension of Metro Line 5, Line 10, Line 11, and Line 12; and newly start the construction of the third phase of the construction planning adjustment line of Metro Line 8, the eastern extension of Line 8, and Line 24.

Accelerate the study of the fourth phase of rail transit construction planning schemes, improve the multi-level rail transit network, and achieve full coverage of important 33 passenger flow corridors. Carry out preliminary research on new low- and medium-volume transportation-related routes, and start construction work in a timely manner.

Guided by the TOD development concept, we will give full play to the maximum effect of "rail transit + land development" and accelerate the development and construction of the city's conditional rail transit station complex.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

It is worth mentioning that the "Planning" for the first time disclosed the new subway lines planned and implemented during the "14th Five-Year Plan" period, and newly started the northern extension of Line 8, the eastern extension of Line 8, and Line 24.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan
Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan
Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

● North Extension of Line 8: The line starts from Jiaoxin Station (formerly Baiyun Lake Station) of the Northern Extension section of Line 8 and ends at Guangzhou North Railway Station, with a total length of 20.7 kilometers and adopts a full underground laying method.

● Eastern extension of Line 8: 18 km of new urban track, from Wanshengwei - Lotus.

● Line 24: The line starts from Jiangfu Station of Line 8 and ends at Memorial Hall Station, with a total length of 20.1 kilometers, and 11 stations are set up in a full underground laying method.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

As of now, the progress of the 10 subway lines under construction is as follows:

Eastern Extension of Line 3 (Panyu Square - Hai ping)

The eastern extension of Metro Line 3 is under construction, the eastern extension of Line 3 is 9.6 kilometers long, extending east from the existing Panyu Square Station of Line 3, with a total of 4 stations on the line, including 1 interchange station, interchange with Line 4 at Haibang Station, and Panyu Passenger Transport Station is located on the west side of the intersection of Asian Games Avenue and Pingyan Road.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

(Note: The above station names are only tentative names of the project, and the standard station names should be subject to the approval and publication of the municipal government.) )

Latest Progress: 42% of civil works have been completed. Of the four stations, 2 have been capped, the remaining 2 are engaged in civil construction, 3 are engaged in civil construction in the 4 sections, and the remaining 1 is undergoing preparatory work. Guangzhou New Town parking lot is prepared before construction.

Eastern Extension of Line 5 (Wenchong - Huangpu Passenger Port)

The line starts from Wenchong Station of Line 5 and ends at Huangpu Passenger Port Station, with a total length of about 9.76 kilometers, with 6 stations in Shuanggang, Miaotou Road, Xiayuan, Baoying Avenue, Guangzhou Development Zone and Huangpu Passenger Port, using 6 train sets, with a maximum operating speed of 90 kilometers, which will realize the rapid connection between our district and the central urban area.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 37% of civil works have been completed. Civil construction will be carried out at 6 stations on the whole line; 4 of the 6 sections will be carried out for civil construction, and the remaining 2 will be prepared in advance; civil construction will be carried out on the access section line and the Shuanggang parking lot.

Western Extension of Line 7 (Guangzhou South - Midea Avenue)

The western extension of Metro Line 7 extends from the guangzhou south station of the first phase of guangzhou metro line 7 in the east to the mid-road station in Shunde District of Foshan City, with a total length of about 13.4 kilometers, with a total of 8 stations and 1 parking lot.

The western extension of Line 7 is one of the key projects of Guangzhou-Foshan City, and it is also the first urban rail transit in Guangzhou to directly enter Shunde with zero transfer. After the completion of the line, it will effectively connect the urban rail transit line network between Guangzhou and Foshan, further expand the interaction scope of Guangzhou and Foshan, and be of great significance for promoting the interconnection and interconnection of the urban rail transit network in the Guangdong-Hong Kong-Macao Greater Bay Area.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest progress: 94% of civil works have been completed, and 89% of mechanical and electrical works have been completed. The rail area of the whole line has been transferred to the "three rights"; the equipment installation and decoration construction has been carried out at 8 stations on the whole line. Electromechanical construction is underway at the Yifeng car park.

Line 7 Phase II (University Town South - Water Northwest)

The second phase of Line 7 starts from University Town South Station and ends at Shuibei North Station, with a total length of 22 kilometers, all of which are underground lines. The second phase of the line has a total of 11 stations in Shenjing, Changzhou, Hongshengsha, Yufengwei, Dashadong, Jitang, Jiazhuang, Kefeng Road, Luogang, Shuixi and Shuibei, of which 7 interchange stations can be interchanged with Suiguan-Shenzhen Intercity Pazhou Branch Line, Line 8 East Extension, Line 13, Line 5, Line 19, Line 6, Line 21 and so on. It adopts a 6-section group with a maximum operating speed of 80 kilometers.

The second phase of Line 7 is conducive to solving the traffic needs of the north-south corridor in the eastern area of Guangzhou and promoting the construction of Guangzhou-Foshan urbanization.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 53% of civil works have been completed. Of the 11 stations, 2 have been capped and 9 are engaged in civil construction; of the 11 sections, 10 are engaged in civil construction and 1 is undergoing preliminary preparation. Civil works were carried out in the Himedo parking lot.

Line 10 (West Lookout - Shibei Bridge)

With a total length of about 19.15 kilometers, the line is an encrypted line for rail transit in the downtown area of Guangzhou, which is conducive to strengthening the connection between the four major groups of Tianhe, Yuexiu, Haizhu and Liwan.

A total of 14 stations are set up, all of which are underground stations, including 10 interchange stations, and the branch line of Line 3 is dismantled; and 1 depot of Guanggang New Town is set up. The vehicle is a 6-car group B vehicle with a maximum operating speed of 80 km/h.

Line 11 (Railway Station - Pazhou - Railway Station)

Guangzhou Metro Line 11 (Guangzhou Railway Station - Pazhou - Guangzhou Railway Station) is a subway ring line, the total length of the line is about 44.2 kilometers, all using underground laying, a total of 32 stations on the line, in addition, a station (city rail Pazhou Station), including 24 interchange stations, 1 Chisha depot.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 66% of civil works have been completed. Of the 32 stations, 1 is in preliminary preparation, 2 have been opened, 8 have been capped, and the remaining 21 are undergoing civil construction; of the 32 sections, 1 has been completed and opened, 8 have been penetrated, 16 have been carried out civil construction, and the remaining 7 have been prepared before construction. Civil construction was carried out on the Chisha Depot and the Entry and Exit Section.

Line 12 (Xunfenggang - South of University Town)

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 31% of civil works have been completed. Of the 25 stations, 3 have been capped, 21 are engaged in civil construction, and the remaining 1 is in preliminary preparation; of the 24 sections, 1 is through, 8 are engaged in civil construction, and the rest are prepared in advance. Civil construction was carried out in the chatou depot and the south parking lot of the university town.

Line 13 Phase II (Chaoyang - Yuzhu)

The second phase of Line 13 runs in an east-west direction, starting from Chaoyang and ending at the Yuzhu Station of the first phase of the project, mainly passing through the core area of the city, and there are key development areas such as Baiyun Lake Area, Luochongwei Comprehensive Renovation Area, Beijing Road Cultural Core Area, Zhujiang New Town, International Financial City, Huangpu Lingang Business District and other key development areas along the line.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 37% of civil works have been completed. Of the 23 stations, 3 have been capped, 18 have been engaged in civil construction and 2 stations have been prepared in advance; among the 23 stations, 3 sections and the entrance and exit lines of the Huanggang parking lot have been completed, 13 have been carried out civil construction, and the remaining 7 have been prepared in advance. Yuzhu parking lot, Huanggang parking lot and cover for civil construction.

Line 14 Phase II (Jiahe Wanggang - Guangzhou Railway Station)

The second phase of Line 14 runs in a north-south direction, starting from Guangzhou Railway Station and ending at Jiahe Wanggang Station, with a total of 8 stations in Baiyun District (excluding the already built Jiahe Wanggang Station), which have stations in Pengbian, Henan, Creative Park, Mawu, Xinshixu, Gangbei, Lejia Road and Guangzhou Railway Station.

Latest Progress: Civil works have been completed by 24%. Of the 8 stations, 1 is capped with the main structure, 5 are engaged in civil construction, and the remaining 2 are in preparation; among the 8 sections, 1 has been penetrated, 4 have been carried out civil construction, and the remaining 3 have been prepared in advance.

The first section of Line 22 (Panyu Square - Chentougang)

The first section (Panyu Square to Chentougang) is 18.2 kilometers long, with a total of about 36.4 kilometers of tracks to be laid, and 4 stations are set up, namely Panyu Square, Shiguang Road, Guangzhou South Railway Station, and Chen tougang.

Latest Progress: Operational commissioning is underway.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

Latest Progress: 31% of civil works have been completed. Of the 14 stations, 1 has been capped, 12 are engaged in civil construction, and the remaining 1 is in preparation; of the 14 stations, 2 are engaged in civil construction and the rest are in preparation. Guanggang New City Depot for civil construction.

In addition, there is a new message from the intercity!

Fangcun to Baiyun Airport Intercity Railway: Civil construction will start

According to the Baiyun District Land Development Center, the Fangcun to Baiyun Airport Intercity Railway Project will also be carried out in stages in the near future, with a planned total construction period of 5 years and 4 months, and is expected to open for trial operation at the end of 2026.

In order to ensure the start of construction of the intercity project, Baiyun District is coordinating the transfer of the pilot land for the Guanghua intercity project, and the groundbreaking ceremony for the project is scheduled to be held in the airport depot of Renhe Town in the near future.

The Fangbai Intercity Project line starts from Fangcun Station and ends at Airport North Station, with a length of about 41.1 kilometers and is laid underground.

There are 10 new stations, namely Rainbow Bridge Station, Guangzhou Railway Station, Baiyun Station, Xiamao Station, Baiyun City Center Station, Fangshi Station, Renhe Station, Airport East Station, Airport South Station, airport north station.

Guangzhou's "14th Five-Year Plan" transportation plan: 3 + 10 planned subways under construction, with a total investment of 650.7 billion yuan

▲ Fangbai Intercity Project Roadmap

The line adopts 8 marshalled urban D-type vehicles, operating on fast and slow lines, with a design speed of 160 kilometers per hour, and operating across the line with Guanghua Intercity.

Fangbai Intercity connects Guangzhou Metro Line 22 to the south into Baietan, connects Guangzhou Railway Station Area, Baiyun Hub Area, Baiyun City Center, Airport Economic Zone, Baiyun Airport, etc. to the north, operates across the line with Guanghua Intercity, connects Baiyun Airport and Guangzhou Main and Sub-Centers, realizes 45-minute access between Nansha and Baiyun Airport, is conducive to promoting the quality improvement and transformation of Guangzhou Railway Station and other areas, and is a north-south backbone express line that supports urban space expansion.

Read on