1. Site cleaning: 2.2 yuan/㎡
Site cleanup includes removing debris, weeds, garbage, etc., to create a clean and safe working environment for construction. The labor quotation per square meter is 2.2 yuan.
2. Excavation: 8 yuan/m³
Excavation refers to the excavation of earthwork materials for site leveling or for other construction needs. The labor quotation per cubic meter is 8 yuan.
3. The rest of the external transportation (within 5km): 14 yuan/m³
Residual transportation refers to the transportation of excavated earthwork materials to a designated location, usually within a range of 5 kilometers. The price of labor per cubic meter is 14 yuan.
4. Rolling in the site: 18 yuan/㎡
In-site rolling refers to the use of equipment such as road rollers to compact the site to ensure site leveling and load-bearing capacity. The labor quotation per square meter is 18 yuan.
5. Site hardening: 80 yuan/m³
Site hardening refers to concrete pouring or other hardening of a site to enhance the durability and load-bearing capacity of the site. The price of labor services per cubic meter is 80 yuan.
6. Drainage trench concrete: 260 yuan/m³
Drainage trench concrete construction includes excavation, pouring, and installation of drainage systems to ensure smooth drainage of the site. The price of labor per cubic meter is 260 yuan.
7. Temporary board room: 360 yuan/㎡
Temporary prefabricated housing refers to the construction of prefabricated houses that provide temporary accommodation and office facilities for construction personnel, including the structural installation and internal decoration of prefabricated houses. The price of labor services per square meter is 360 yuan.
8. Floor tiles: 40 yuan/㎡
Floor tiles refer to the work of tiling indoor and outdoor floors, including the cutting, laying and gap treatment of tiles. The price of labor per square meter is 40 yuan.
9. Water and electricity: 50 yuan/㎡
Hydropower installation includes the installation and commissioning of water pipes, wires, switches, sockets and other facilities in the construction site. The price of labor per square meter is 50 yuan.
10. Gypsum board of board room: 28 yuan/㎡
The gypsum board construction of the board house refers to the installation of the gypsum board ceiling inside the board house to improve the comfort and practicability of the board house. The price of labor services per square meter is 28 yuan.
The above is the labor quotation analysis of the temporary construction project of the expressway in 2024, and the costs are calculated in accordance with the market price and industry standards for reference. During the actual construction process, the specific cost may vary depending on the change in region, material and labor costs.