(Reporter from Midong District Rong Media Center: Ye Zijie reports) The new projects and continuation projects in Midong District have entered the golden period of construction, and the project sites have accelerated the construction progress on the premise of ensuring the quality of the project to ensure that the project is completed and put into operation on schedule.
On July 8, the reporter saw at the construction site of Xinjiang Shuangxi Shiwang Door Industry Co., Ltd. that the workers were stepping up construction, and the site was busy.
Fu Changjun, the person in charge of the construction of the project, said: "After the project officially started in late April this year, the construction of each single body has been steadily implemented, and now the construction of steel structures in two factories is being intensified, and the office building has been built to 2 floors, we will speed up the construction of the plant and office building while ensuring the quality of the project, and complete it as scheduled at the end of October, so that the project can be put into operation as soon as possible." ”
It is understood that the project is an annual output of 200,000 sets of high-end entrance doors and special doors (windows) construction, with a total investment of more than 2,000 yuan.
Yang Jianfa, project leader of Xinjiang Shuangxi Shiwang Door Industry Co., Ltd., said: "At present, the work of the project is progressing steadily. At the end of this year, the equipment will be hoisted and commissioned, and it will be put into production at the beginning of 2025, with an estimated annual output value of about 30 million yuan. ”
At the construction site of the production and construction project of prefabricated steel structure parts and steel structure bridges in Xinjiang, construction workers cooperate with each other and are completing the work before the formwork support and bundling on the pile foundation.
"The construction of the office building officially started on July 1 this year, and the pile foundation and other infrastructure construction have been completed, and the next step of construction will be carried out," said Mustapa Imam, the construction director of the project. Our building materials are entered in advance, and all construction links are accelerated under the premise of ensuring quality and safety, and the main construction is planned to be completed in October this year. ”
According to reports, the total investment of the project is 100 million yuan, and in October last year, the construction of three production plants has been completed.
Baturjan Suleiman, general manager of Xinjiang Tingzhouyuan Industrial Technology Co., Ltd., said: "In August this year, the equipment can be installed and debugged in the factory, and it is planned to carry out trial production at the end of September, and it is expected to be officially put into operation in October, with an annual output value of more than 9,000 yuan, providing diversified steel structure products for the construction of projects in various parts of the autonomous region, and also contributing to the economic development of Midong District." ”
"At present, new projects and continued projects in the jurisdiction are rushing to catch up with the schedule, and the community should continue to do a good job of visiting enterprises, understanding and grasping the progress of the project in detail, and working with relevant departments to provide intimate services for the construction of the project, so that the project can be completed and put into operation as soon as possible." Lei Yang, director of Ruikang community, said.