Chuanguan News Reporter Zhao Rongchang Luzhou Observation Guo Huilin Zhang Yaoren Rong Media Center, Jiangyang District, Luzhou City, text/picture/video
Target locking
This year, Luzhou plans to invest a total of 361 key projects in the city, involving a total amount of 701.59 billion yuan and an annual planned investment of 115.03 billion yuan. As one of the major livelihood projects, Shandong Provincial Hospital Luzhou Hospital, after the National Day, the secondary structure construction team has also entered the site and continued to increase the number of workers, and it is planned that the main structure will be capped within the year, and the comprehensive medical institutions covering Yunnan, Guizhou, Sichuan and Chongqing provinces (cities) will be further put into use.
Shandong Provincial Hospital Luzhou Hospital will achieve the capping of the main body within the year.
Sprint to the scene
In October, the temperature dropped, and the construction site of Luzhou Hospital, Shandong Provincial Hospital, Jiangyang District, Luzhou City, adjusted the daily operation time from October 8: from the original irregular "operation system" due to high temperature weather to 6 am to 18 pm every day.
As one of the key construction projects of the fifth batch of regional medical centers in China, the project will comprehensively improve the overall diagnosis and treatment level and treatment capacity of difficult and critical diseases in the Yunnan-Guizhou-Sichuan-Chongqing junction region, and build a national regional medical center for trauma, endocrine and metabolic diseases "based in Sichuan, radiating to the southwest, and facing the whole country".
The schedule is reversed, and the sprint is imminent. How is the project progressing? The reporter visited the site.
More than 60 secondary structure operators entered the venue
After the National Day holiday, Zhang Liang, the representative of the construction agency responsible for the on-site construction and the person in charge of the Luzhou Hospital project of Shandong Provincial Hospital, the second center of Luzhou Municipal Government's investment and construction project management, was busy every day.
Almost every day, "new faces" report to the project. "It is necessary not only to register these workers, but also to carry out safety operation training before taking up their posts." At 14 o'clock on October 14, more than 20 minutes after seeing Zhang Liang, he stopped what he was doing and said hello to reporters.
Following Zhang Liang into the project construction site, the sizzle of welding sparks and the jingle of making pouring frames were endless. Nearly 500 workers divided labor in an orderly manner to speed up the construction of independent foundations and raft structures.
"After the National Day holiday, more than 60 secondary structure operators have entered the stadium." Zhang Liang told reporters.
Workers carry out secondary structural work.
What is a secondary structure worker? Zhang Liang explained that the secondary structure operation refers to some non-load-bearing masonry, structural columns, lintels and other parts that need to be completed before decoration in the frame, shear wall and frame shear project. These structures include infill walls, ring beams, structural columns, waterproof anti-beams, roofs, infill walls, partition walls, etc.
"Take the hospital as an example, the secondary structure operation is to divide the originally empty main structure of the entire floor into various unitized wards." Zhang Liang added.
Shandong Provincial Hospital Luzhou Hospital is jointly built by Shandong Provincial Hospital and Luzhou Hospital Affiliated to Southwest Medical University, relying on the superior teaching resources of Shandong First Medical University and Southwest Medical University, aiming to build a high-level clinical diagnosis and treatment center. The project covers a total area of 108 acres, with a construction area of 146,000 square meters, 1,000 designed beds, and is expected to receive 650,000 patients per year after completion.
Zhang Liang introduced that the project, which officially started construction in April this year, has been completed more than 90,000 square meters. Among them, the emergency medical technology building with a total of 7 floors has been built to the top floor of the main structure, and is expected to be completed this month; The planned 17-storey inpatient building has been built to 11 floors and is expected to be topped out in mid-to-late December.
The "progress bar" of decoration preparation work has been pulled to 90%
Shandong Provincial Hospital Luzhou Hospital Project was undertaken by Chengdu Construction Engineering Group First Construction Engineering Co., Ltd. In the past few days, Zhao Wei, the project leader of the contractor, went to Chengdu every other day for decoration matters.
"Soon after the start of the secondary structure of the project, the decoration work will be started simultaneously, and it is now a critical period to prepare for the decoration work." Zhao Wei introduced that because the hospital project is different from other construction projects, it has higher requirements for decoration materials.
Shandong Provincial Hospital Luzhou Hospital.
"Whether it's a decoration material supplier or a construction team, each one has to go through it personally." Zhao Wei explained that for the decoration design of the hospital, the design should fully consider the needs and experience of patients, and ensure that every detail can bring convenience and comfort to patients. For example, in the renovation of the patient room, pastel tones and warm décor will be used to create a peaceful, relaxing atmosphere; In common areas, comfortable seating and convenient self-service facilities will be added to alleviate patient anxiety.
The importance of renovation preparation is also reflected in the impact on the schedule. "Decoration is about acceptance and delivery, and it is also about putting it into use." Zhao Wei added, "It is more about whether the surrounding radiation people can enjoy better medical resources as soon as possible."
According to the relevant person in charge of the Luzhou Municipal Development and Reform Commission, after the completion of Shandong Provincial Hospital Luzhou Hospital, it will give full play to the advantages of Shandong First Medical University and Southwest Medical University, two eastern and western universities, and gradually realize the all-round homogeneous development with Shandong Provincial Hospital through the translation of the five elements of brand, technology, management, talent and platform.