With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

author:Beiqing Community Newspaper Sub-Center Edition
With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

The reporter of Beiqing Community Daily (WeChat ID: tongzhoushequbao) learned that recently, the first high-speed rail large-diameter shield tunnel in the sub-center of the sub-center of the sub-center of the Jingtang Intercity Railway successfully completed the shield machine tunneling task and achieved breakthrough. This important progress marks the completion of all tunnel projects of the Jingtang Intercity Railway, laying a solid foundation for the opening and operation of the entire railway line.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

The Jingtang Intercity Railway is an important intercity high-speed railway connecting the Bohai Rim region and the Beijing-Tianjin-Hebei region, starting from the comprehensive transportation hub of Beijing Sub-central Station and ending at Tangshan Station in Tangshan City, Hebei Province. The total length of the railway is about 148.7 kilometers, with a maximum design speed of 350 kilometers per hour, and there are 8 stations along the line, including Beijing City Sub-center, Yanjiao, Dachang, Xianghe, Baodi, Yutiannan, Tangshan, Tangshan, etc.

Among them, the section from Yanjiao to Tangshan has been put into operation on December 30, 2022, and the second phase of the Beijing sub-center section of the project is in full swing.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

Large-diameter tunnels with double tracks in the future

When you take the elevator to a place more than 20 meters underground, you will see a circular tunnel with a diameter of more than 10 meters.

As the first high-speed rail large-diameter shield tunnel in the sub-center of Beijing, the Yuntidal River Tunnel has a total length of about 1.3 kilometers, which is almost twice the diameter of the subway project.

In the future, this tunnel will be paved with two tracks, the upper and lower tracks of the Jingtang Intercity Railway.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

On December 28 last year, the domestic super-large shield machine "Jingtong" was launched, with an excavation diameter of 13.3 meters.

On June 25 this year, on the third basement floor of the comprehensive transportation hub of Beijing City Sub-central Station, the "Jingtong" shield machine ejected the receiving shaft without any difference, and gloriously completed the task of crossing the "one river, one road, one cultural relic" underground.

After the tunnel is completed, the Jingtang Intercity Railway will be connected to the station structure at the east end of the integrated transportation hub of the upper and sub-central stations.

There are also some ancillary works in the subsequent tunnel, such as ditches, cable troughs, etc., which need to be constructed, and then the construction of the under-track structure and the track will be carried out.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

Sun Lijun, head of the Jingtang Intercity Railway Project of China Railway 14th Bureau, said that the north side of the "Jingtong" shield machine tunneling line is adjacent to the existing Beijing-Harbin railway line, and the nearest horizontal distance is only 19 meters, and there is an average of one train passing by every 5 to 15 minutes.

In order to ensure the smooth progress of the project and the safety of the existing line operation, the project team adopted high-precision Beidou satellite positioning technology to carry out safety monitoring of the railway subgrade, and strictly controlled the working radius and station position of the on-site construction equipment to ensure that there was no impact on the existing line catenary. The all-weather measurement data and digital intelligent command center are used to guide the shield machine to move forward accurately and smoothly, and the error is controlled at the millimeter level.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

Efficient promotion of project construction

In the future, it will go directly from Tangshan to the sub-center

The reporter learned from the Tongzhou District Major Project Coordination Service Center that in order to promote the smooth development of the land volume work for the construction of the Jingtang Intercity Railway, the District Major Project Center "prescribed the right medicine", and the main leaders of the center led the team to conduct in-depth research, detailed analysis, form a special report, and propose a solution path, and finally efficiently solved the obstacles to the land volume work of the Jingtang Railway (Beijing Section) involving 3 towns and 6 administrative villages, ensuring the smooth progress of the project.

With a total length of 1.3 kilometers, the tunnel of the sub-central section of the Jingtang Intercity Railway has been completed, and the whole line will be opened soon

In the future, after the completion of the Beijing sub-center section of the Beijing-Tangshan Intercity Railway, it will be of great significance to implement the Beijing-Tianjin-Hebei coordinated development strategy, enhance the overall economic competitiveness of the region, and serve the convenient travel of the local people.

Beiqing Community Daily is comprehensively compiled from: Beijing Tongzhou Publishing, Beijing Transportation Subscription Account