A production order specifies which material is to be produced, where it is to be produced, which operations are required to do this and on which date production is to take place. It also defines how the order costs are to be settled. 也负责决定订单的费用如何决定。
S/4HANA的生产订单既可以手动生成,也可以基于一个planning order自动生成。
As described in this procedure, production orders can be created manually without being previously requested. Alternatively, they can be automatically created by converting a planned order. During requirements planning (MRP run), planned orders are created at every BOM level to cover requirements.
在需求计划阶段(即MRP run阶段),planned order在BOM级别被创建,负责承担费用。
事务码CO01:
维护必填字段Material,即待生产的物料
生产工厂ID: 2800
Order Type PP04:
- REL:Released
- PRC: Pre-costed
- DISB: Distributed to MES
- MANC : Material availability not checked
- SETC Settlement rule created